Upgrade all floor switching equipment and install wireless on Floors 1 & 6 as well as 1 AP per floor during the annual data center shutdown (Which is generally for Fire, UPS, Generator, Cooling Maintenance) all while 2 new 10 Ton A/C units are being added to the DC to make the total cooling capacity 100 tons and a crane lifts the heat exchangers to the roof.

What we installed...

2 Cisco 4506 SUPV's
14 Cisco 4506 SUPII+
15 Terminal Servers from Perle
25 Access Points
14 New Racks
2,800 Patch Cables consumed
6 Cisco 1242AP's
21 Cisco 1131AP's


Big Crane

 

Before the Floor Switch Upgrade Project
Picture 059.jpg
Spaghetti
Picture 060.jpg
Vermicelli
Picture 061.jpg
Fettuccini
Picture 062.jpg
More Cable Pasta
Picture 063.jpg
And More
Picture 064.jpg
Someone once thought this was a good idea

down with plastic cable ties!!!
Picture 065.jpg
Can you see the equipment
Picture 066.jpg
One of the best pre conversion floors
Picture 067.jpg
Nuts to find a bad cable
Picture 068.jpg
Dead equipment couldn't be removed

because of the cables
Picture 069.jpg
Wow..
Picture 070.jpg
More..
Picture 071.jpg
More
Picture 077.jpg
Worse yet.. the IS Floor
After the Floor Switch Upgrade Project
DSCF0461.JPG
How many devices we removed
DSCF0484.JPG
One of 14 Closets we upgraded
Rotation of DSCF0483.JPG
Looking into the floor closet from the hallway
Rotation of DSCF0467.JPG
In June we are redoing the core..

so this is temporary
Rotation of DSCF0468.JPG
$80K worth of Cisco on the Floor

This equipment runs and routes the floors
Rotation of DSCF0469.JPG
LAN/WAN row in the Data Center